Home on Tennessee Creek No Longer Threatened by Back Yard Shoreline Soil and Land Erosion

Project Name

Ross Residence on Possum Creek, a tributary of the Tennessee River #115

Customer Name
The Ross Family

Design / Specifying Engineer
Design/Build

Block Manufacturer
Bradley Tank and Pipe, LLC in Cleveland, TN

Wall Installer
Chattanooga Hardscapes

Project Location
Soddy Daisy, Tennessee

Year Built
2010

Project Scope

By Tyler White, President of Chattanooga Hardscapes

When Barry Ross' family purchased a home on Possum Creek near Chattanooga, Tennessee, Barry knew the shoreline needed some work. The existing retaining wall (part brick, part railroad tie) was rotting and crumbling away, exposing the shoreline to wave action and boat wakes. Every year, more of the Ross' yard was lost to the lake and in 2009, it was time to tackle the erosion issue once and for all.

My business, Chattanooga Hardscapes, specializes in retaining walls—primarily on residential projects. When Barry contacted us and we came on site, the old cross tie wall was about 50 percent gone and had allowed extensive erosion of the yard. Over the years, the ties had fallen into the river and the erosion just kept getting worse. While the erosion wasn't a threat to the house, it was unsightly and the owner wanted to prevent additional erosion of his property.
Initially, we considered going with a 125 lb. stacking block that had been used by several adjacent properties, but the blocks weren't available in the area anymore. The next available size was an 85 lb. block, but Barry wanted to be absolutely certain the wall would not need replacing in the near future. When I saw the scope of this project, I recommended using 2,500 lb. Redi-Rock blocks. I had seen Redi-Rock used in several shoreline protection projects in the past and I knew that the scale of the system basically guaranteed that the wall would never move. That's a definite plus at a site that has seen at least two retaining wall failures in the past.

In addition to building a new retaining wall, the homeowner wanted a system that would allow him to integrate a new dock as well. The wall design called for about 270 Redi-Rock blocks which would stretch along the property's edge—a distance of approximately 200 ft.

Barry took care of the permitting process through the Tennessee Valley Authority (TVA). TVA Act 26A governs construction on the shoreline of the Tennessee River and its tributaries. It was an extremely wet winter here in Tennessee, so we began construction in January of 2010 when the water levels were the lowest of the year.
Bradley Tank and Pipe, the local Redi-Rock manufacturer, helped design the project and determined that the wall could be built as a gravity structure due to the massive scale of the blocks.

Using Redi-Rock cut down on our installation time significantly, because the one-ton blocks are set by machines rather than by hand. At 7.5 ft. tall, the wall didn't require reinforcement, which also minimized the amount of excavation the project required and the time. Our crew consisted of myself and one installer and our equipment included a mini excavator and a skid steer loader.

To begin construction, we installed a one ft. deep gravel footing before installing the first course of blocks, which were buried according to Bradley Tank and Pipe's design. The wall site was a challenge to access; we had to unload the blocks from the delivery truck using the skid steer, then haul them about 300 yards through the woods on a trail we cleared to the staging area. We would line up ten to 15 blocks, and then and I would begin maneuvering the blocks into place using the excavator. The installer was attaching the lift chain to the blocks and guiding them into place.

After we installed the footing and first course of blocks, a very heavy rainstorm caused the water level to rise about six feet over the top of the blocks—which made us a little concerned for the stability of the wall since it wasn't yet finished. When the water level finally dropped again though, the wall hadn't settled even a fraction of an inch; we were very pleased.

The design called for a foot of gravel backfill behind the wall, but in some places we put in up to 5 ft. of gravel based on how much soil had eroded. We wrapped permeable fabric behind the gravel backfill, under the footer and against the back of the blocks to help ensure that the drain stone could do its job.

The wall only took us about 23 working days to install—but due to rain delays, those 23 days were spread over the course of two months. This was our first Redi-Rock wall, but it was easy to install because it's like stacking Legos—really big Legos. That made it fun and easy to work with and we enjoyed the process a lot.

After the entire wall was up, we installed rip rap along the base for the entire length of the wall and wrapped it around the ends of the wall about three feet.

"We've had very favorable comments from neighbors and friends since the new wall was finished," Barry said. "And of course it improves the neighborhood by replacing the unsightly wall that was there previously."

Design Manual

Find us on Facebook and share your landscape photos with us!
Join our group on LinkedIn to ask and answer questions about big block retaining walls!

Case Studies

Amphitheaters (2)

Bridges & Culverts (10)

DOT Jobs (11)

Military (4)

National Accounts (9)

Other (2)

Parks (10)

Railroads (3)

Residential (14)

Road Construction (16)

Sports Complexes (4)

Water Applications (26)