Reinforced Walls Protect Power Plant From River Erosion

Project Name

VELCO/GMP Lime Kiln Substation

Customer Name
Vermont Electric Power Company (VELCO) and Green Mountain Power Corporation (GMP)

Design / Specifying Engineer
Engineers Construction, Inc.

Block Manufacturer
Redi-Rock Walls of New England

Wall Installer
Engineers Construction, Inc.

Project Location
South Burlington, Vermont

Year Built
2010

Project Scope

THE CHALLENGE

When Vermont Electric Company (VELCO) and Green Mountain Power Corporation (GMP) set out to build a new substation in South Burlington, Vermont, the site slated for the project presented some daunting challenges.

The site was located on a steep bank directly adjacent to the Winooski River. Also, a transcontinental ATT fiber line ran through the center of the site and needed to be relocated before construction could begin. In addition, an existing 115 KV line and a 46 KV line ran directly overhead. To further complicate construction, two significant railroad bridges were located adjacent to the property, as was a hydroelectric dam.

THE SOLUTION

From the beginning, the need for tall, strong retaining walls to create a level building space was evident. The problem was that the initial design did not account for the existing conditions of the site.

"They wanted this done before we even started, so we had to come up with some creative ways to put this wall up quickly and efficiently," explained project manager Aaryn French of Engineers Construction. Part of that solution was choosing Redi-Rock retaining walls to create a level site for constructing the new substation.

VELCO and GMP chose Redi-Rock for the project based on several factors, including Engineers Construction's recommendation based on previous projects successfully completed with Redi-Rock. "We were experienced in using Redi-Rock and are confident in the product’s abilities," French explained. Redi-Rock is a large block retaining wall system known for its ability to build tall gravity walls, and even taller reinforced walls. Each massive, one-ton Redi-Rock block engages with the block above and below it using a knob and groove system—creating walls that stand the test of time. The natural rock texture on the face of Redi-Rock blocks gives finished walls a natural, aesthetic look.

"The initial challenge was that this was an old waste site, so the existing material was unsuitable as a foundation for the walls. We had to dig all the overburden off the rock to get down to good rock. But we quickly discovered that it was solid ledge that sloped towards the river," French explained.

THE DESIGN

The design of the project evolved as the project progressed. "The initial design looked great on paper, but when we got on-site we had to adapt the design to match the leveling pad we had to put in to accommodate the ledge," French said. The final design called for two, geogrid-reinforced Redi-Rock Limestone retaining walls—one 760 ft-long wall that stood 27 ft. high at its highest point, and another 240 ft.-long wall that stood 16.5 ft. tall at its highest point. The longer wall included a radius on one end and a 90 degree turn into the slope on the other end. The base of the walls was above the flood plain, so the wall design did not need to account for river flow.

THE CONSTRUCTION

To create a foundation for the retaining walls, Engineers Construction designed and excavated the ledge to reshape it using mechanical devices and blasting. Then, they installed rock anchors into a 700 cubic ft. concrete leveling pad. The rock anchors extended 6 ft. into the ground at intervals of twelve inches for the entire length of both walls. Since the leveling pad had to follow the contour of the land, several "steps" were required. "The steps were challenging based on the way the Redi-Rock went together. We had to really be careful where we located the steps so that they coincided with the dimensions of the blocks," French said.

One of the ways Engineers Construction kept the project on schedule was installing the Redi-Rock blocks directly from the delivery truck onto the wall. Redi-Rock installs like giant Lego blocks, using an installation crew and a backfill crew. For this project, the crews used a Link Belt TCC 450 telescopic crawler crane to install the blocks as well as backfill. Each block was placed in less than a minute, allowing the entire 21,200 sq. ft. wall to be installed in just 12 days.

French specified 16,000 yards of 1.5 in crushed stone to backfill behind the walls. Using crushed stone expedited installation because it required less compaction than gravel and also provided additional drainage. Reinforcing the walls required 5500 sq. yd. of SF 80 geogrid and 6500 sq. yd. of SF 110 geogrid.

"Once we got started, we were installing 10-12 loads a day," French explained. That equals roughly 325 Redi-Rock blocks, or 1,900 sq. ft. of walls installed every day for 12 days. From a production and delivery standpoint, Redi-Rock Walls of New England did an outstanding job of coordinating efforts to meet the needs of this challenging project.

This project recieved a "Rocky Award" for Commercial Project of the Year in 2010. Projects from across North America competed for this honor.

If your next project needs a proven solution on a tight deadline, choose Redi-Rock. For tall gravity walls and even taller reinforced walls, Redi-Rock builds solutions for critical projects across the globe. Visit our engineering pages for more engineering information and assistance.

Design Manual

Find us on Facebook and share your landscape photos with us!
Join our groups on LinkedIn to ask and answer questions about big block retaining walls!

Case Studies

Amphitheaters

Bridges & Culverts

Channels

Developments

DOT Jobs

Marinas

Military

National Accounts

Other

Parks

Railroads

Residential

Retention Ponds

Road Construction

Shoreline

Sports Complexes

US Army Corps