TX Family Protects Home From River Flooding
Project Name: Vista Del Rio Wall #103
Customer Name: Vista Del Rio Residence
Design / Specifying Engineer: Civil Solutions Group, LLC
Block Manufacturer: SI Precast, Inc.
Wall Installer: Structures Hardscapes Specialists, Inc.
Project Location: San Antonio, TX
Year Built: 2008
Hold Back the Flood
THE CHALLENGE:
After a San Antonio area resident’s house was flooded three times by the Guadalupe River, he knew it was time for a change. Looking for higher ground, he bought property several miles upstream and started making plans for a retaining wall to protect his investment.
The new property was located approximately 20 ft. above the normal river level and consisted of a run of approximately 525’ along the river’s edge. On this property, the homeowner made plans to build a new home, a swimming pool and tennis court.
After seeing several failing retaining walls adjacent to the new property, the owner knew he needed something different—something engineered. The goal the owner had in mind was to provide a suitable construction area on top of the walls, in addition to protecting as many of the existing trees as possible. In addition, two requirements ruled the design of the wall—it needed to be a retaining wall that wasn’t going to fail and it had to look good.
THE SOLUTION:
To provide a shoreline protection solution, the general contractor, the Elan Group, contacted Redi-Rock manufacturer SI Precast to take a look at the site and come up with an engineered a solution.
Redi-Rock is a retaining wall solution that utilizes massive, one-ton blocks to harness the power of gravity and built tall walls 15 ft. or taller without reinforcement. Even taller walls are possible with Redi-Rock’s patented geoconnector. Redi-Rock has a proven track record in water application projects. The wet-cast concrete design of the blocks makes it hold up even in areas with freeze-thaw issues. Redi-Rock walls are available in three textures—Limestone, Cobblestone and the new Ledgestone texture—which give walls the “Essence of Natural Rock” look.
To design a solution for this project, the team called in Design Technician Phil Fassler from Civil Solutions Group (CSG) and Jeremy Banken, President of Structures Hardscapes Specialists (SHS) from Minneapolis to evaluate the site in person and come up with a realistic solution for the project.
The general contractor took Fassler and Banken on a water tour of the area surrounding the new home site. What the group found was a hodge podge of shoreline protection measures including stone and mortar walls and concrete bag walls. “These walls looked terrible and were all crumbling and allowing erosion,” Fassler explained.
The paramount consideration for the wall solution was what to do about the base of the retaining walls to prevent the river from undermining it. Michael Johnson, PE and President of Civil Solutions Group determined that the most effective solution would be to use sheet piling at the base of the walls. This allowed the area to be de-watered prior to wall construction. The loose river silts could then be excavated and replaced with competent material upon which to build the retaining walls.
The Redi-Rock wall design CSG drafted consisted of a two tiers which gave the home easy access to the riverfront. The design also provided the building space required for the home on top, and was the most aesthetically pleasing solution for the site parameters because it allowed for landscaping and a stairway. The walls, which stand approximately 9 feet tall each, are spaced about 15 feet apart. The lower wall is reinforced with geogrid, and the upper wall is a gravity wall. An additional 19.5 ft. tall reinforced wall completes the shoreline protection on the property.
By using Redi-Rock, CSG was able to design the upper tier of the retaining wall as a gravity wall. The massive size of each Redi-Rock block and the interlocking design reduced the amount of geogrid required, which saved on installation times and costs in addition to saving existing landscaping.
In water applications, there are two main factors that will determine whether a wall will fail or stand the test of time—the base and the backfill. Civil Solutions Group initially came on site, they discovered the river bottom was soft silt and clay at least three feet down.
Before construction of the wall could begin, a crew needed to divert the flow of the river around the construction site. To accomplish this, they constructed a sheet pile dam. The sheet piling extended 15 feet down into the river bed, providing a stable anchor for the wall.
Sheet pile construction began by a local contractor about two weeks prior to SHS showing up at the site and was approximately 75 percent complete when the retaining wall construction began. SHS excavated a ramp down to the sheet piles in order to conduct the earth work preparation necessary for the wall construction. SHS dewatered area behind the piles with pumps and excavated the loose material, then placed geotextile fabric in the bottom of the excavation. SHS filled the trench with crushed stone up to the base elevation for the lower tier.
The crew constructed the lower (reinforced) wall by cutting the embankment back approximately 18 ft. in order to provide room in which to operate their equipment. Geogrid reinforcement was placed behind the 28 in. deep Redi-Rock units and the reinforced area was filled with select granular material to minimize any settlement potential of the upper tier and the construction of the home.
The upper tier was constructed as a gravity wall using 41 in. and 28 in. deep Redi-Rock units. As each course of blocks was installed, SHS performed the second requirement for a successful retaining wall in a water application—they backfilled using crushed stone as specified by CSG. Adequate, engineered backfill prevents hydrostatic pressure from building up as the water levels rise and fall.
The tiered walls ended at the staircase location. The 19.5 ft. tall reinforced wall was constructed the remaining distance to the property line and allowed the home owner to incorporate a boat house into the wall project.
The wall design at this location was pushed farther back into the property to provide a recess for the boat house that would remove it from the main flow of the river—thus better protecting the boat. This solution also helped to satisfy the Corps of Engineers, whose approval was required. The Corps was concerned about restricting the river flow with new construction along the water way. To meet the Corps requirements, CSG’s design took a little area from the north end of the property/river limits, and gave some area back on the south end of the property to maintain the balance of water flow.
THE OUTCOME:
In total, the 525 lineal ft. wall took about three weeks to install. The wall was completed in early 2008 and has seen two flood seasons come and go. Still, the 12,000 sq. ft. walls remain level and perfectly intact.
To learn how Redi-Rock performs in water applications, check out the Water Drag Shear information or Water Application brochure. Or, call 866-222-8400.
Design Manual
The Redi-Rock Design Resource Manual is an invaluable resource for any engineer or architect designing a Redi-Rock wall.
Download the Redi-Rock Design Resource Manual today! Due to large file sizes, we've split the DRM into several sections which you can download here:
Gravity Walls: 41"_ 60"_ 9" Setback
Reinforced Walls: 28" Series and PC System
Case Studies
Amphitheaters (2)
Bridges & Culverts (10)
- IN Historic Bridge Restoration
- Ledgestone Headwalls Protect Wetlands
- Abutments: OH Gravity Walls Protect Bridge
- Fast Abutment Installation in TN
- Abutments: OH Ledgestone Walls Install Fast
- Nova Scotia Bridge, Amphitheater
- UT Winding Mountain Bridge
- Gravity Abutments for Private Bridge
- Ski Resort Wing Walls, Retention Pond
- Wing Walls: OH Gravity Walls
DOT Jobs (11)
- Walls Solve MS DOT Right of Way Issue
- Tenn. DOT Highway Construction
- DOT Retaining Wall on the Ohio River
- Freestanding Walls for Freeway Landscape
- 9" Setback Walls for MI Road Construction
- Quick DOT Rest Area Construction
- Erosion Control Wall in Washington DC
- Aesthetic DOT Gravity Wall in VT
- CO DOT Chooses 13' Redi-Rock Wall
- Shoreline Erosion Control for Road Construction
- Reinforced DOT Wall in MA
Military (4)
- Shoreline: Veterans Park Construction
- US Army Mosque Training Facility
- Weapons Testing Range
- Buffalo VA Hospital
National Accounts (9)
- Walls for Hospital Parking Expansion
- Railway Construction and Maintenance
- Railway Construction in West Virginia
- Cobblestone Parking Lot Construction
- Home Depot Maximizes Space
- Home Depot Gravity Wall
- McDonald's Saves on Wall
- Costco Revitalizes Parking Area
- Gravity Walls Mazimize Wendy's Parking
Other (2)
Parks (10)
- Baseball Sports Complex Design
- Shoreline: Veterans Park Construction
- Shoreline: OH Island Erosion Solution
- Channel: Tulsa Stormwater Drainage System
- Private Club Pool Foundation and Wall
- Channel: Protecting Park from Creek Erosion
- Marina: Mackinac Island Harbor
- DOT Retaining Wall on the Ohio River
- Outdoor Stage with Columns
- Nova Scotia Bridge, Amphitheater
Railroads (3)
- Railway Construction and Maintenance
- Railway Construction in West Virginia
- Chicago Train Track Reinforcement
Residential (14)
- Shoreline: Vancouver Island Sea Walls for Home
- Ledgestone Retaining, Freestanding for KY Home
- Back Yard Landscaping Emergency
- Shoreline: ID Wall Prevents Erosion at Home
- Shoreline: TN River Home Erosion Control
- Channel: KY Stormwater Drainage
- Shoreline: IN Ledgestone Walls Protect Home
- Shoreline: MI Home Reinforced Walls
- Beautiful Residential Estate Retaining Wall
- Shoreline: Erosion Control for WA Home
- Custom Tennis/Basketball Court for Home
- Tall Walls, Spiral Staircase
- Shoreline: TX River Flood Protection
- Shoreline: MT Home Stops Shore Erosion
Road Construction (16)
- Gravity Wall Stops Cemetery/Road Erosion
- WA City Reduces Right of Way
- Ledgestone Wall for Road and Street Construction
- Ledgestone Wall for Highway Construction
- 19.5 Ft. Ledgestone Gravity Wall in Cinci
- Cobblestone Masonry Wall Restoration
- Ledgestone Headwalls Protect Wetlands
- Tenn. DOT Highway Construction
- DOT Retaining Wall on the Ohio River
- UT Winding Mountain Bridge
- Freestanding Walls for Freeway Landscape
- Walls for Hospital Parking Expansion
- Shopping Development Retaining Wall
- Quick DOT Rest Area Construction
- Erosion Control Wall in Washington DC
- Ski Resort Wing Walls, Retention Pond
Sports Complexes (4)
- Baseball Sports Complex Design
- NE Patriots Stadium/Shopping Center
- Custom Tennis/Basketball Court for Home
- U of Idaho Stadium Access Walls
Water Applications (26)
- Abutments: OH Gravity Walls Protect Bridge
- Abutments: OH Ledgestone Walls Install Fast
- Channel: Tulsa Stormwater Drainage System
- Channel: Tulsa Downtown Storm Solution
- Channel: NE City Reduces Flooding
- Channel: CO River Diversion
- Channel: KY Stormwater Drainage
- Channel: Protecting Park from Creek Erosion
- Marina: Mackinac Island Harbor
- Marina: Erosion Control for 31 Acre Marina
- Marina: Peecast Walls Replace Failing Wood
- Pump Station: Intake Structure Walls
- Retention Pond: OH Park Pond/Bridge
- Shoreline: Vancouver Island Sea Walls for Home
- Shoreline: IN Ledgestone Walls Protect Home
- Shoreline: ID Wall Prevents Erosion at Home
- Shoreline: Veterans Park Construction
- Shoreline: OH Island Erosion Solution
- Shoreline: TN River Home Erosion Control
- Shoreline: MI Home Reinforced Walls
- Shoreline: Walls Protect Power Plant
- Shoreline: Erosion Control for WA Home
- Shoreline: TX River Flood Protection
- Shoreline: Branson Sea Walls
- Shoreline: MT Home Stops Shore Erosion
- Wing Walls: KS Walls Protect Dam